Foundations are complete. Concrete slabs in the building are complete. Foundation waterproofing, damproofing, and insulation is substantially complete. Foundations are being backfilled. CMU block work for the stair towers and elevator are out of the basement and up to level two. They will be completed after 2nd floor framing is installed. Underslab electrical and ductwork is complete. Slab pours for slabs on grade in the building are complete. Geothermal well drilling is complete. South access road prep is complete. Timber framing of the West wing is substantially complete and the crew will move to the North wing next week.
The pedestrian bridge is in progress. Framing in the residential wing is in progress. The site contractor will continue with utility work outside the building including tel/data, electrical, and geothermal distribution and earth duct installation.
The team remains focused on the milestone of weather tight by the end of September and continues to work the crews long days and Saturdays to reach this goal.
Stick Framing
Timber Framing
This comment has been removed by the author.
ReplyDeleteAmazing content, thank you for sharing!
ReplyDeletehttps://www.excavationdoneright.com/excavation-lexington-ky