April
saw sheetrock tape sand and prime progress through the building. The Elevator installation went very
smooth. Flooring and millwork was in
full swing. We started commissioning
meetings and put together a start-up testing balancing and commissioning
schedule to ensure a smooth completion.
We added a dedicated resource to start the work to complete list for all
rooms in the building as part of a pre-punchlist process. The schedule continues to track very well
to the original completion date.
Looking
ahead at May we will begin our equipment start-ups and systems balancing. Commissioning meetings will continue. Millwork and flooring will continue. Finish paint will follow.
[lab]
[lab]
[lab prep]
[entry tower]
[seminar casework]
[seminar casework]
[commons kitchen]
[commons kitchen]
[commons wood ceilings and fieldstone fireplace]
[commons wood ceilings]
[faculty apartment wood flooring]
[faculty apartment deck]
[dorm room lighting controls]
[bathroom tile]
[bathroom tile]
[polished concrete in bathrooms]
[stone stair tower]
[greenhouse controls]
[courtyard]
[courtyard]
[courtyard patio and sunshade]
The Better Co is a home construction company which helps you build your dream home.
ReplyDeletehouse construction cost calculator
Very good information, I dedicate myself to the realization of stabilitamerica.com
ReplyDelete